TATARSTAN 3

Construction of deep processing of "Oil Refining and Petrochemical Complex" in Nizhnekamsk (Step 1.3-1.5)

Sector: Industry

Status: Under Implementation

The project is designed to process heavy carbon oil with high sulfur content, produced in the territory of Tatarstan. The main objectives of the project:

  • Organize the economic efficiency of the depth of processing of raw sour petrochemical production organization scheme with a wide range of high-quality motor oil and petrochemical products, meeting international quality standards and environmental requirements;
  • Replacing crude oil export of high-quality products with high added value, in line with the course of the Energy Strategy of Russia until 2030;
  • Improving the competitiveness of the Russian market of petroleum products;

  • Creation of new jobs in the construction and operation of the complex.

The project started in 2013 and involves the construction of the Complex Gidroochistok, ultrasonic testing, Aromatica complex, isomerization unit, catalytic cracking, other facilities. As of 01.07.2015, the project under construction. Design work is underway, placed orders for manufacturing equipment. Under construction and installation work. Projected completion dates - 2017-2020 years (depending on the stage of construction)

Jobs: 2,766

Total budget: 116,518 million rubles. (VAT included); 98,744 million rubles (without VAT)

It is planned to invest in the project: 69,942 million rubles.

Location: Nizhnekamsk
Payback Period: 5.6 years